Jehu wrote:What if this 'addition' was installed by someone with the appropriate qualifications? And what side of the PV system does this apply to? Would you really need to get a licensed installer to put up a few more panels after the original system was installed? From memory, you do not need to have any qualifications to work on something if it is under 50V DC or 110V AC. Ok, the currents are pretty high but if you follow the standards for isolating circuits it's pretty safe.
Tracker wrote:Of certainty, I can say that the voltages we are talking about are NOT elv and hence require correct handling to remain legal.. It is a requirement of the local supply authority to approve of any grid-connected devices.
Not much else to comment upon.
I was going to say exactly the same thing. Any more than one 170W+ panel and you're over the 50VDC value. I'm not 100% sure on the specifics of the DC voltage limits before it changes from ELV to LV but I could easily look it up in the AS3000 definitions but I left my copy at work.
As for adding extra panels, EA's ES1 document clearly states that 1. Alterations or additions to a generator are required to be submitted for approval prior to being undertaken (same form as used for the initial application) and 2. To be elligible for Solar Credits (ie: minimum 60c/kwh)
the system needs to be installed by a Clean Energy Council accreditted installer using approved panels and inverter(s). It might be that the inverter you'd need to use (for three sources) may not even be approved for use in Australia. I only know of two similar inverters - Sunny Backup which provides UPS-style backup when the grid fails, and Latronics I believe have an inverter which accepts wind and solar inputs on the one device.
Onto some of your other queries...
Jehu wrote:My family and I want to get a grid connect system for our home. We want solar and wind and we know that's all well and good but we want a little extra. Is there any issue with the feed in tariff and laws with connecting a biodiesel generator to the system to maximize the amount of power we can pump into the grid?
<snip>
Also when they say that the system can only be a 10kW system, are they basically saying that we could theoretically produce 240kWh per day at 10kW per hour x 24 hours?
I'm surprised Tracker didn't ask what state you're in as different states have different legislation. Assuming NSW, and in EA's area, you would not be permitted to have both wind and solar generation and still be elligible for gross metering. Alternative generation types may be acceptable, however EA's ES1 document only elaborates on the requirements for solar generation when net or gross metered. One of the other conditions is a limit of 10kw generator size. This is the NSW legislation (I don't have a link to it from home so you'll have to wait until I email it to my home email from work as I've cc'ed the link to numerous installers and customers) and EA's ES1 document implies the limit is an instantaneous output (ie: maximum peak of the inverter(s)). I believe they also keep an eye on the total panel kw but have not seen any that have 10kw inverter total and >10kw panel total... yet. My system inspection work instruction gives some examples of what is and isn't permitted, so you'll have to wait until Monday before I can make reference to it too. Interestingly, Integral Energy seem to be permitting systems with >10kw inverters (two 6kw) but up to 10kw of panels...
Then again, alot of what I've mentioned may not be relevant if you're in a different state or distribution area...
"The standard you walk past is the standard you accept".